What is the G99 Fast Track Process?

The G99 Fast Track process can help you connect your small generation or storage faster than a formal application.

To qualify, your generating unit(s) must meet one of the three categories of Small Generation Installations as a single generator installation:

Small Generation Installation 1

  • Basic design capacity is 32A (7.36kW) or less.
  • Registered capacity is 16A (3.68kW) or less.
  • Total registered capacity is 16A (3.68kW) or less.
  • No EREC G100 Export Limitation Scheme is required as the manufacturer's export limit is factory-set via the inverter.

Submit Form A3-3

Small Generation Installation 2

  • Basic design capacity is 32A (7.36kW) or less.
  • Registered capacity is 16A (3.68kW) or less.
  • Total registered capacity is 32A (7.36kW) or less.
  • An EREC G100 Export Limitation Scheme may be required, limiting export to 16A (3.68kW).

Submit Form A1-2

Small Generation Installation 3

  • Basic design capacity must be 32A (7.36kW) or less (generating unit – inverter or battery).
  • Registered capacity is 32A (7.36kW) or less.
  • Total registered capacity is 60A (14.72kW) or less.
  • An EREC G100 Export Limitation Scheme may be required, limiting export to 32A (7.36kW).

Submit Form A1-2

Additional requirements

You must also include Phase to Neutral Loop Impedance information using this form .

For extra support, click here .

Please note, you cannot connect until you receive confirmation that our assessment is complete. After this, the installer has up to 3 months to install and commission the generation. Once finished, they must submit Form A3-2 to the network operator within 28 days.

What next?

Please send your completed form and any required supporting information to G99FastTrack@sse.com. Check the frequently asked questions section below to see what supporting information we need to help speed up your application. 

We aim to respond within 10 working days. 

Frequently asked questions

Get in touch

Would you like to speak to us before you apply or have a question about an existing application?  

Our team is available to help guide you through your generation journey. If you would like to speak to us we are here Monday to Friday 08:00 - 17:00.